For the 470 cells, If I had GDSII layouts would it be a batch operation to get minimal electric cells for manual placing and automatic routing?
Electric has a built-in facility for this (you could run it yourself). It takes a GDS file and a LEF file. The GDS has layers and the LEF has export locations. Then Electric merges the two to produce a library. I can do this or you can do it yourself. So it is relatively automated, but you have to get the GDS layers right, find the right libraries, etc.
-Steve