Hi Wei,
On 30.09.21 12:04, Huang Wei wrote:
> Hi Marcus,
>
> Thank you very much for the detailed explanation.
> Basically, in my case, the two repeat blocks will be connected to two USRPs
> separately,
> and they are operated through two PCs. So sharing one repeat block might not
> be very
> practical.
ah, ok. That's really a very different problem.
> My thought was, when you first execute the transmission, the two channels are
> synchronized
> until you change the repetition factor in the two repeat blocks. Is it
> possible that each
> time the repetition factor changes, the whole flowgraphs restart just like I
> click the
> execute button at the beginning, then they are synchronized again?
No, because the timing of the restart would be random.