From: Juan Pechiar
Subject: Re: [O] deadline :: schedualed :: or-later
Date: Mon, 29 Aug 2011 08:48:10 -0300
User-agent: Mutt/1.5.20 (2009-06-14)

Hi Michael,

Please check the purpose of SCHEDULED in org-mode:

   http://orgmode.org/manual/Deadlines-and-scheduling.html

It is exactly what you mean by starting at a day or later.

For a fixed date, just drop a timestamp inside a heading.

Regards,
.j.

On Mon, Aug 29, 2011 at 01:38:26PM +0200, Michael Hintz wrote:
> IMHO it needs a 3nd date-mode. I use deadline for all thinks
> that have to be done until the deadline-date. I use scheduled
> for a fix date ...
>
> and what about thinks that could start at a date "or later".
>
> I tried to fix it by using a time for fix and no time for
> non-fixed or has-to-be-start dates, but this is no solution,
> because there are todos that have to be done on a fix-time and
> others only on a fix day.